PRE – OPENING CHECKLIST AND ACTIONS
Dev: DANG TRONG DAI – ICTSO.TOP
Deadline Month Before Opening Description Action Progress Status Remarks
+ 5 Months -4 -3 -2 -1 0 +1 +2 +3 +4
X All Documentation for
X General Information
X Manuals
X - Welcome Charter +
X Product Standards
X - General Manager
X X Agenda
X X - Human Resources
X X - Financial
X X - Rooms Division
X X - EPIC Core Values
X X - Hotel Security
X X - Hotels Food Safety
X X - Hotel Pools
X Ensure knowledge of
product manuals and
subsequently distribute
them to department /
section heads for
Execution
X X X X X X X X X Follow up actions
defined in the pre-
opening manual
X X Work Site to follow up:
X - Site Photographs
X - Mock-up rooms
X - Work site meetings
- Progress reports
Project: Opening Date: Date: Month No: